13.5 MW Distillate Oil operating in Tuscola, MI — Midcontinent Independent Transmission System Operator, Inc..
13.5 MW
Nameplate Capacity
5
Generators
units
Petroleum Liquids
Technology
1968
Operating Since
Coordinates
43.4566, -83.1890
County
Tuscola, MI
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | DTE Electric Company | DTE Electric | — |
| Owner(s) | DTE Electric Company | DTE Energy | — |
| Status | Operating | — | — |
The Wilmot plant is a 13.5 MW petroleum liquids-fired power plant located in Tuscola County, Michigan. The plant began operating in 1968 and consists of 5 generators utilizing petroleum liquids technology. It is owned by DTE Energy and operated by DTE Electric Company. The plant operates within the Midcontinent Independent Transmission System Operator, Inc. (MISO) balancing authority and the ReliabilityFirst Corporation (RFC) NERC region.
In the most recent year with available data, the Wilmot plant generated 552 MWh of electricity, resulting in a capacity factor of 0.5%. According to available data, the plant's installed cost was $143.01 per kW. The Wilmot plant ranks 9th out of 26 similar plants in Michigan and 272nd out of 886 nationally. Financial data is sourced from FERC filings.
Generated from EIA, GEM, and public data sources
NERC Region
RFC
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc..
Grid Voltage
40 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
0 MWh
Latest Month
552 MWh
Annual Generation
0.5%
Capacity Factor
$166/kW
Installed Cost
$-667.4/MWh
Operating Cost
DTE Electric Company
Reporting Utility
Annual Capital & Operating Expenses
Cumulative Installed Cost
Per-Unit Cost Trends
Market Position
ISO/RTO Market
MISO
LMP Node
DECO.WILMTP11
Pricing Hub
MICHIGAN.HUB
Location Type
Generation Node
Node Source
Curated node match
DTE Energy says it expects Saline data center approval later this month, has more deals in negotiation
DTE Energy's fast-track approval request for a $7 billion Oracle and OpenAI data center in Saline Township has led to protests over...
DTE wants power deal for $7 billion data center approved by Dec. 5: 'False sense of urgency'
DTE Energy's move for expedited approval of Saline Township data center prompts concern from environmental advocates and Michigan's attorney...
Data centers eyed in at least 10 Michigan towns. How they might change state
The data center rush is on in Michigan; At least 10 communities have been approached by data center developers, while utilities are quietly...
As DTE seeks speedy approval to power massive data center, some officials push back
DTE officials say their plan to provide power for a massive Michigan data center project does not need to go through the typical regulatory...
Last updated 2026-03-14